Timeline

February 2019
Committees and working groups established.
April 2019
Background and Work Plan prepared.
June 2019
Initial Data Collection, Gap Analysis, Final Work Plan completed and prepared.
April 2020
Draft narrative report including initial drafts of Working Group Reports completed.
April 2020
Additional data collection and analysis completed.
June 2020
Final narrative report including final drafts of Working Group Reports completed.
July 15, 2020
Final Report prepared for submission on August 4, 2020
August 5, 2020
Caltech's TPR report is due.
October 14-16, 2020
WSCUC Thematic Pathway to Reaffirmation site visit and team report.
February 2021
WSCUC review and final recommendation to be received.